Here is a sample of some VBA code that will populate the Task Text30 field with the numbers of the baselines for which each task has values saved. This is useful if you are using lots of the baselines but not all your tasks have had all the baselines saved.

For example:

image

“Task” has values in Baseline, Baseline2, Baseline4 and Baseline9 while “Other Task” only has values in Baseline2.

 

   1:  Sub WhichBaselinesSaved()
   2:  Dim t As Task
   3:  Dim i As Long
   4:   
   5:  For Each t In ActiveProject.Tasks
   6:      If Not (t Is Nothing) Then
   7:          t.Text30 = ""
   8:          For i = 0 To 10
   9:              If i = 0 Then
  10:                  If t.BaselineStart < 50000 Then
  11:                      t.Text30 = t.Text30 & i & ", "
  12:                  End If
  13:              ElseIf Not t.GetField(Application.FieldNameToFieldConstant("Baseline" _
  14:              & i & "Start", pjTask)) = "NA" Then
  15:                      t.Text30 = t.Text30 & i & ", "
  16:              End If
  17:          Next i
  18:          t.Text30 = Left$(t.Text30, Len(t.Text30) - 2)
  19:      End If
  20:      
  21:  Next t
  22:  End Sub
Comments
  • Thank you for your macro. I mentioned your blog and this macro tip on my website September 25, 2009.

    Don

    donwlarson@gmail.com

Your comment has been posted.   Close
Thank you, your comment requires moderation so it may take a while to appear.   Close
Leave a Comment