Finish date of project plan may change in Project 2003

Finish date of project plan may change in Project 2003

  • Comments 3
  • Likes

clip_image002 Finish date of project plan may change in Project 2003

Problem description
When a project manager selects Sync to Protected Actuals after processing the updates that are submitted by resources, the Finish date of the project may change by several days.

Solution Information

This Fix it Solution automates enabling UpdatedSyncActuals.